International Power-led consortium to acquire UAE power-water plant
An International Power-led consortium has agreed to acquire 40 % of the Umm Al Nar power and water plant in Abu
Dhabi, UAE. The agreement includes an extension to the plant and an arrangement that the entire output of the plant
will be sold to the Abu Dhabi Water and Electricity Company (ADWEC) under a 23-year agreement.
International Power, along with Tokyo Electric Power Company (TEPCO) and Mitsui & Co., has agreed to acquire a 40
% equity interest in the Umm Al Nar water and power plant from the Abu Dhabi Electricity and Water Authority (ADWEA).
The remaining 60 % ownership interest in the plant will continue to be held indirectly by ADWEA.
The consortium has also signed agreements to expand the plant and sell the entire power and water output to the Abu
Dhabi Water and Electricity Company (ADWEC) under an approximate 23 year Power and Water Purchase Agreement
(PWPA).
International Power will own 50 % of the consortium investment vehicle, which equates to a 20 % equity interest in
theplant. International Power's equity investment will be a maximum of £ 56 mm ($ 88.4 mm).
The plant will be operated and maintained by an operating company (which will be owned 70 % by International Power
and 30 % by TEPCO) under a long-term Operation and Maintenance contract for the entire term of the PWPA.
"This agreement represents a very good opportunity for us to capitalise on our strengths in the region, through both
the operation of existing plant and the development and construction of new plant," said David Crane, CEO of
International Power.
"We have been working closely with excellent partners, namely ADWEA, who are also our partner and customer at our
other project in Abu Dhabi (Shuweihat S1), together with TEPCO and Mitsui, and we believe this project will be a
great success," he added.
The total project cost (comprising the cost of acquisition and the cost of the expansion project) is estimated at $
2.1 bn (£ 1.4 bn), which is to be funded by a mix of non-recourse project finance debt, shareholder equity, and
cash inflow from operating the existing plant. The mandated lead arrangers for this financing plan, which comprises
both conventional long-term and short-term debt, include Bank of Tokyo Mitsubishi, HSBC, Gulf International Bank,
ING, Sumitomo Mitsui Banking, West LB, National Bank of Abu Dhabi and First Gulf Bank.
Like the Shuweihat S1 project, which was the first power and water project to use a combined conventional and Islamic
financing structure, this project will also be supported by an Islamic loan facility, which will be arranged by Abu
Dhabi Islamic Bank. Financial close is expected in June 2003.
The consortium's total equity commitment to the project is estimated at a maximum of £ 112 mm, which will be
shared by the partners in ratio of their ownership interest. International Power owns 50 % of the consortium
investment company, TEPCO 35 % and Mitsui 15 %.
Audited information relating to the book value of existing plant, and past profits attributable to the asset being
acquired is not available, as this acquisition is part of Abu Dhabi's power and water privatisation process.
Located close to Abu Dhabi city, the gas-fired Umm Al Nar plant has an installed capacity of 850 MW for power and is
capable of producing 162 MIGD (Million Imperial Gallons per Day) of desalinated water.
Under the terms of the PWPA with ADWEC, the consortium will also develop a new gas fired power and water plant
adjacent to the existing plant. This new facility will have an installed power and water capacity of 1550 MW and 25
MIGD, respectively.
The engineering, procurement and construction contract for the new plant has been awarded to Mitsui, with Toshiba and
Hitachi Zosen as principal sub-contractors for the power and water plant respectively. The new plant will be
constructed using GE9FA turbines and Multi-stage Flash desalination technology. Construction will commence in the
third quarter of 2003 and commercial operation is expected by mid-2006.
On completion of this newfacility, seven of the existing (but relatively new) desalination units totalling 69.5 MIGD
will be integrated with the new water plant, taking the total water capacity of the new plant to 94.5 MIGD. In
mid-2008, the remaining existing water and power units will be handed back to ADWEA for decommissioning, leaving the
final size of the Umm Al Nar plant at 1,550 MW and 94.5 MIGD. For a two-year period when the new extension and the
existing power and water plants are running concurrently, the total contracted capacity at the site will be 2,200 MW
power and 143 MIGD water.
The consortium is pleased to have signed an approximate 23-year “take-or-pay” Power and Water Purchase
Agreement with ADWEC. This contract, which will cover 805 MW and 157 MIGD of the existing Umm Al Nar plant, will take
effect on completion of acquisition. Under the terms of the contract, ADWEC will also purchase the entire output from
the new plant when it reaches commercial operation.
As per the terms of the PWPA, fuel will be procured and paid for by ADWEC. This acquisition is anticipated to reach
completion by June 2003 and is expected to be immediately earnings accretive for International Power.