Oil sands companies still hesitate on projects despite falling costs
Costs in Canada's pricey oil sands are starting to fall but nervous developers are still leery of giving the green
light to stalled projects. Earlier, Husky Energy said estimated costs for its proposed Sunrise oil sands development
-- a joint venture with BP -- had nearly halved to C$ 2.5 bn, from earlier projections of C$ 4.5 bn. The company is
the first to provide hard numbers but there is plenty of informal chatter of cost savings within Alberta's oil sands
following the wave of project cancellations and delays at the end of last year.
"We're hearing anecdotally that costs are down 20 %, 25 %," but Husky's new estimates provide a concrete point of
reference, said Steve Fekete, a Calgary-based senior principal at consulting firm Purvin & Gertz.
Until recently, oil sands companies were pursuing projects with swollen, multibillion-dollar budgets, confident at
turning a profit with crude prices above $ 100 a barrel. Inflation soared as companies flocked to exploit Alberta's
massive crude reserve -- the biggest outside Saudi Arabia -- and by last summer, analysts reckoned that the costs for
a typical oil sands project had more than quadrupled since 2003. But when crude oil prices collapsed, so did project
economics and nearly C$ 200 bn ($ 164 bn) worth of proposed developments have been affected, according to recent
estimates by Merrill Lynch.
Fewer projects mean less competition for a limited pool of labour, while global steel prices have slumped more than a
third from last year. But most companies still need $ 80 a barrel crude to push ahead with new projects, and the
speed of the oil price plunge is likely to render company executives much more cautious at restarting developments
even after prices recover.
"There's going to be some hesitation," said Justin Bouchard, an oil sands analyst at Raymond James. The example of
Long Lake, a joint development between Nexen and OPTI Canada, is the "worst-case scenario," Bouchard said.
Building at the peak of the oil sands boom, the C$ 6.1 bn project -- like nearly all others -- saw several delays and
cost overruns, only to start production after crude prices had crashed below $ 50 a barrel. The partners have since
pushed back a decision to double output to after mid-2010.
Sticky costs
And some costs are "stickier" than others. Labour was the main culprit for escalating inflation during the boom
years, as companies fought over a limited pool of experienced workers and as inexperienced staff dragged down
productivity rates. Costs are coming down but the savings aren't in cutting labour rates.
Flint Energy Services, for example, is stripping out perks such as retention bonuses, while the bigger local pool of
skilled labour removes the need to bring in workers from elsewhere. This will cut costs by 10 %, Flint's chief
executive Bill Lingard said in March, and productivity gains will save another 10 %.
But persuading workers to take lower wages is tricky, and any changes in labour rates certainly haven't matched the
dramatic decline in commodity prices. Enbridge Chief Executive Pat Daniel noted recently that labour rates "have not
changed, and generally... don't tend to come down all that much."
He added: "We have seen a fairly significant change in productivity... [as inexperienced people] have been pushed out
of the workforce."
However, these cost savings can only benefit companies if projects go ahead. Imperial Oil -- majority-owned by
cash-rich supermajor ExxonMobil -- is still keen to proceed with plans for its Kearl oil sands mine, unlike many of
its competitors. Other companies are hoping to lock in lower prices by renegotiating and rebidding contracts during
the downturn. Suncor Energy, among others, has noted greater bargaining power with contractors that have seen work
suddenly dry up. But these savings may evaporate if companies restart projects at the same time, kicking off the
inflationary spiral once more as too many developments compete for too few workers.
"There are so many projects waiting to be built... and everyone is very aware of how tight labour is," Raymond James'
Bouchard said. "That's going to put a damper on how quickly these projects get going again."
In the meantime, companies with existing output are focusing on lowering operating costs. Suncor has already seen
costs fall and is targeting further cuts of up to 15 %, CEO Rick George said earlier.
"For the oil sands in general, operating cost reductions are largely achieved by improving reliability," said Chris
Feltin, a vice president at Tristone Capital Corp. "That's what Suncor is aiming for -- ensuring that they're running
their operations as smoothly as possible."
