Imperial Oil approves Canadian oil sands project
Imperial Oil recently announced that it would proceed with the first phase of the C$ 8 bn Kearl oil sands project, a
surface mining and bitumen extraction operation about 70 km northeast of Fort McMurray, Alberta.
The company plans to develop Kearl in three phases with production from the first phase beginning in late 2012 at an
average 110,000 bpd of bitumen. Construction costs are about C$ 4.50/bbl of bitumen recovered, according to Imperial
Oil. It expects production to increase to about 300,000 bpd of bitumen upon completion of all three phases.
The company estimates that the project area contains near the surface an estimated 4.6 bn bbl of bitumen recoverable
with open-pit mining methods that include large-scale electrical and hydraulic shovels, trucks, and double roll
crushers.
The operation involves mixing the crushed oil sand with water to form slurry that enters a bitumen extraction
facility. The facility separates the bitumen as a froth, which is mixture of bitumen, water, and fine solids. The
froth then enters the froth treatment plant that produces saleable bitumen.
Imperial Oil currently has no plans to include an onsite upgrader. For shipping the bitumen through third-party
pipelines, it will reduce the bitumen's viscosity by adding a diluent, such as a natural gas condensate.
The Alberta government approved the project in May 2007, and Canada's federal government approved it in August 2007.