Cairn reports on production rise at Mangala field in India
Oil production from Mangala field in Rajasthan, India, has reached 20,000 bpd from five wells as work progresses to
expand capacity of a processing terminal, reports Cairn Energy.
The field, part of a complex that includes nearby Bhagyam and Aishwariya fields, started up last August and averaged
15,430 bpd in fourth quarter 2009.
A 30,000-bpd train is on line at the Mangala Processing Terminal (MPT), which eventually will have four trains with
total capacity of 205,000 bpd and room for expansion. Approved plateau production for the complex is 175,000
bpd.
Start-up of two more trains will expand MPT capacity to 125,000 bpd by the end of June.
Production now moves by truck to the Gujarat coast for shipment in heated tankers to refineries operated by Reliance
Industries and Mangalore Refining & Petrochemicals.
Cairn India is commissioning a 590-km, 32-inch insulated pipeline between the MPT and Salaya, near RIL's 660,000-bpd
and 580,000-bpd refineries at Jamnagar, heated to keep the crude oil temperature above 65 degrees Celsius.
At Mangala, the company has drilled 45 producing wells, of which 33 have been completed in the Palaeocene Fatehgarh
formation and are producing or awaiting start-up. Three of the wells are horizontal. The company has been operating
two rigs and a completion unit in the Mangala development area and soon will add a third rig.
Cairn also has drilled eight wells in Raageshwari Deep gas field, production from which combines with Mangala
associated gas to fuel steam turbine generators at the MPT and heaters for the crude pipeline. The company said one
Raageshwari well, Raag-14, tested gas at a field-high rate of 15.7 mm cfpd after a hydraulic frac.
Construction is complete on the Raageshwari gas terminal, about 80 km south-southeast of the MPT, and facilities 20
km southeast of the MPT to produce water for secondary recovery.
Cairn has a pilot project testing enhanced recovery with polymer and alkaline-surfactant-polymer injection, which the
company estimates might boost recovery from the Mangala complex by 300 mm bbl.
